Home
Site General Info
LR Members Info
General & History Info
Buildings & Structures
Operations
LOCOMOTIVES
Rolling Stock
Photo Galleries
Home
Site General Info
LR Members Info
General & History Info
Buildings & Structures
Operations
LOCOMOTIVES
Rolling Stock
Photo Galleries
The Llangollen Railway's History
Above: Visiting '1F' no 4422 at Glyndyfrdwy with a demonstration freight train during
1996.
(John Rutter)
There was hardly a pause for breath before 'Project X' restarted, perhaps better
called 'Project Y' or even 'Project XI'; the next target being Glyndyfrdwy. In early
1990, reconnaissance began, and it was decided that it was time the signalbox (recovered
from Leaton some time previously) had track outside it again. Tree cutting and trackbed
clearance took a long time, and various members of the team were involved in the
signalling in Llangollen Station at the time. The signalling at Llangollen Station
was approved by Major Olver on 3rd May 1991, enabling trains to pass at both Llangollen
Station and at Goods Junction. Twelve months of hard work had seen a 17-lever Dutton's
Cambrian Railway frame installed, with GWR lower quadrant signals. It was commissioned
on 30th June.
Above: (left) The site of Glyndyfrdwy sidings in 1988. On the right, the rough grassy
area is the trackbed, which runs to the left of the signalbox. The original station
building is the prominent slate-roofed building on the left. (right) 1991, and the
line has reached the site of Glyndyfrdwy sidings.
(Dave Southern and John Rutter)
The platforms had been demolished on closure, and the site grassed over as a childrens'
playing field. Excavation revealed the base of the original platforms, onto which
the new platforms were built - the remains of the original ones can still be seen.
In late 1990 a very dilapidated building was dismantled and recovered from Northwich,
where it had been in use as the engine drivers' mess until it became derelict. This
was re-erected on the new Up platform in 1992 to serve as the station building; the
original station building being in private hands.
Above: (left) Excavations underway in the station revealed the bases of the original
platforms. Again the original station building can be seen on the left. (middle)
A pause for breath during tracklaying. In the background, the skeleton of the 'new'
station building can be seen. (right) The new level crossing which had to be built.
(Bill Shakespeare and John Rutter)
Track laying began in March 1991, and moved on at high speed, with all the materials
being available. Sleepers had been stockpiled at Glyndyfrdwy, from where they were
loaded onto a lorry with a 'Hiab' and taken to the rail head. Rails were taken by
rail from Llangollen to the rail head, where they were unloaded and towed by a tractor
to the site. By 24th May 1991, track was laid to within half a mile of Glyndyfrdwy
village; 100 60-foot panels were laid in 9 weeks. The first works train arrived on
Sunday 21st July, although of course much work remained to be completed. A few weekends
later the level crossing was laid.
Above: (left) Tamping the ballast on the Glyndyfrdwy extension. How much the methods
have changed since the late 1970s! (right) First train on the extension - the LMS
inspection saloon is hauled by the Jinty. (John Rutter)
The first public passenger train to Glyndyfrdwy since 1964 arrived on 17th April
1992, headed by Foxcote Manor. Subsequent work included the installation of the rest
of the signalling and a footbridge, and completion of platform two. The station and
signalbox received the an Ian Allan National Railway Heritage Award in 1995, the
"Keighley and Worth Valley Railway" award for the best project carried out by volunteers.
A plaque was unveiled in the station building on 27th December 1995 by Graham Mitchell,
chairman of the KWVR.
Above: Glyndyfrdwy in 1998, with rebuilt platforms, completed signalling, station
building brought from Northwich, and footbridge from Welshpool. Resident pannier
7754, owned by Llangollen Railway Trust, heads West towards Carrog. (Dave Southern)
Llangollen Railway History
Above: (left) Carrog station before restoration got underway. Note the lack of buildings
on platform two (on the left) or signalbox on platform one. (right) Track between
the platforms once more. (LRT archives and John Rutter)
Before the Carrog extension was even started, the station building came up for sale,
and was bought by a member of the Railway. A group called 'Friends of Carrog' was
set up to organise the restoration of the station itself, and this got underway before
the actual tracklaying began. (see separate Friends of Carrog site) GWR materials
were recovered from sites around the country, and restoration of the buildings got
underway.
Above: Another general view of the station with restoration underway. (John Rutter)
In 1993, ICI at Runcorn came up with an offer to donate track, due to a new plant
being built on the site of some of their sidings. This included around ¾ mile of
track, plus points and buffer stops. Recovery continued through the latter half of
the year, some of the materials being used to replace life-expired track laid when
the line reopened to Berwyn in 1985. A diversion for the P-way department was the
upgrading of the line to a 22-ton axle loading to allow for the visit of Flying Scotsman
that year.
Above: The railhead just West of Glyndyfrdwy, (left) looking East towards Glyndyfrdwy
station, and (right) looking West along the Dee, the trackbed being on the left.
(LRT archives)
Work began in mid-July 1994 on the Carrog extension, the first mile being constructed
with new flatbottom rail on concrete sleepers, these being purchased. Ballasting
of this section was helped out by 30 members of Customs & Excise staff as a team-building
exercise over one weekend in September! However, continuing grant problems meant
that donated bullhead rail from ICI was used for the second mile instead. Tracklaying
was halted on 25th June 1995 due to problems with the supply of rails from ICI, as
building work on their site blocked access for removal of the rails, the next load
not arriving until 18th October.
Above: Laying sleepers on the extension; loading at Carrog and unloading at the railhead.
(John Rutter)
In the meantime, the first mile of track was inspected by HMRI, also on 18th October,
and passed to enable a DMU train to work along it for the October 1995 diesel gala.
This first train left Glyndyfrdwy heading West on 22nd October, and tracklaying resumed
the following day.
By late January 1996, the passing loop in Carrog station was progressing well, with
only 100 yards of track missing between the track laid in the station and the railhead
of the single line back to Glyndyfrdwy. The gap was bridged on 4th February.
Above: Looking from the road bridge over the Railway at Carrog. (left) rebuilding
underway and (right) freight train at Carrog during Transport Extravaganza 1998.
(John Rutter)
The final inspection on 28th April saw Colin Law, HMRI Inspecting Officer, approve
the extension, shortly followed by the official re-opening on 2nd May. This despite
the 1995 leaflet having Carrog as our Western terminus! A train for Trust members
and plc shareholders, consisting of the two suburban coaches and standard 4MT 76079,
departed at 10am. This was followed by a train for VIPs at 11am, consisting of the
Belle stock hauled by Foxcote Manor and 5080 Defiant.
Llangollen Railway History
Beyond Carrog, Corwen was the next town served by the Ruabon to Barmouth line, and
is the target for the Llangollen Railway's next extension. The trackbed is largely
intact, with only relatively minor work required to clear the way through. A small
halt was also provided to serve Bonwm, a tiny village between Carrog and Corwen.
Above: (left) The trackbed just before Bonwm, looking East towards Carrog. A cutting
has been filled in, hence the steep gradient. The sign shows that the A5 is close
by to the right. (right) Looking towards Corwen. The River Dee is close by on the
right, and the A5 is behind the trees on the left. (George Jones)
Above: Hedge laying near the site of Bonwm Halt. (Graham Ross)
Above: (left) The track gang in action, laying track Westwards from Carrog. (right)
25313 shunts wagons onto the new section of track for storage before heading for
ballasting duties on Berwyn viaduct. (Barney Barnfield and Pete Sheridan)
The extension to Corwen is progressing well. The Transport and Works Order is in
place and the project split into Phase 1 and Phase 2, due mainly to funding requirements.
Phase one is to complete the running line to a temporary single platform, approximately
300 yards east of the location for the new Corwen Station. No run-around loop will
be possible due to the width of the embankment at this point, so push pull, DMU or
Autotrain operation will be required. To date (Oct 2011) the space for the platform
has been cleared and fencing along the length of the trackbed is almost complete.
Tracklaying is in the planning stage.
Phase 2 will require the injection of significant monies and will consist of the
construction of the new station and associated works.
If you would like to get involved in this important project, either as an existing
member of Llangollen Railway Trust, or as a new member, you will need to have a PTS
certificate to make sure you are safe working trackside, and abide by all the safety
rules applying to a ‘Construction Site.’ All time spent volunteering needs to be
recorded as it is counted towards the ‘matched funding’ for the project.
For more detailed infomation please contact Anne-Marie, Deputy Station Master at
Llangollen.